Excavation and Ground Preparation


Excavation of building foundation, basement, and fence.

Requirements

  1. Application Form signed by owner / applicant, signed and sealed by Engineer, Forms are available at the Office of the Building Official
  2. Excavation Plans signed by the owner / applicant , duly signed / sealed by Engineer
  3. Updated PTR / PRC of Engineers
  4. Photocopy of valid ID of the owner (Preferably Government Issued ID)
  5. Notarized Authorization Letter to transact in behalf of the owner or SPA from owner
  6. (5) Sets notarized Bill of Materials / Cost Estimate
  7. (5) Sets notarized Specifications
  8. Locational Clearance from City Zoning Office
  9. Construction Safety and Health Program (CSHP) approval from DOLE
  10. Secretary’s Certificate (For Corporation)
  11. (1) Logbook
  12. (2) Long Folders (White)
  13. Certified True Copy of Transfer Certificate of Title from the Registry of Deeds

As Required

14. Construction Business Permit from BPLO ,Contractor’s Business Permit or City Tax (For Non-Contractor)
15. EPNRO Clearance (For Need to Cut Trees)
16. Fire Safety Evaluation Clearance (FSEC) from Alabang Fire Department